Oswego County Airport nets $200k grant

Plans to expand the Oswego County Airport are primed for take-off. The New York airport received a $200,000 grant to replace the airport’s on-site septic system and utilize wastewater infrastructure from the city of Fulton. Removing the septic system opens up the door for the county to build a new hangar that could house up

Construction on Indiana Airport Project Takes Off

Ohio-based architecture and engineering firm Woolpert has been contracted by the Dubois County Airport Authority to provide engineering, design and construction services for a $12 million runway extension at the Huntingburg Regional Airport. The project is being funded by federal, state and local grants.

Missoula airport terminal project advances with funding boost from FAA

Construction is advancing on the new passenger terminal at Missoula International Airport, the first phase of which remains on pace to open by January 2022. The airport had initially budgeted just $5 million in discretionary funds for the terminal, though airport director Cris Jensen said the FAA could award the project its full $20 million

Dayton International Airport celebrates upgrades at terminal

The Dayton International Airport celebrated the completion of the first phase of a terminal modernization project. This phase of the project cost nearly $29 million. Among the updates is a reconstructed front drive, new lighted bollards, added access, and replaced the old canopy with a modern glass canopy. There’s a new valet and shuttle bus

Port Authority Approves Billions for Airport Projects

The Port Authority of New York and New Jersey on Thursday advanced a series of long-awaited construction projects at the region’s three main airports. The board approved $445 million for construction and planning work at John F. Kennedy International Airport, which is about to undergo a massive overhaul of its roadways, taxiways, terminals and gates.

New York’s LaGuardia unveils new $3.9 billion Delta terminal

Delta is spending around $3.3 billion for the redesign while the Port Authority of New York & New Jersey is pitching in a significant chunk of change too — about $600 million. The terminal is only one part of an $8 billion renovation that’s pushing the entire airport closer to Grand Central Parkway.

$518 million CLT airport lobby expansion plan approved

The Charlotte City Council Monday night agreed to spend more than $500 million to expand the lobby of Charlotte Douglas International Airport. The 175,000-square-foot expansion will include larger security checkpoints, additional ticketing and baggage claim areas, more lobby space, an outdoor canopy and two pedestrian walkways, according to the airport.